EX0-112 · Question #5
What is an objective of the process Change management?
The correct answer is A. making the correct decisions on the implementation of changes to the information provisioning. Change Management's primary objective is decision-making - determining which changes should be approved and how they should proceed, making A correct. Options B and C describe activities that belong to Change Implementation or operational execution processes, not Change…
Question
What is an objective of the process Change management?
Options
- Amaking the correct decisions on the implementation of changes to the information provisioning
- Bdetailed monitoring of the progress of the changes
- Cmanaging the implementation of the changes
How the community answered
(35 responses)- A91% (32)
- B3% (1)
- C6% (2)
Explanation
Change Management's primary objective is decision-making - determining which changes should be approved and how they should proceed, making A correct. Options B and C describe activities that belong to Change Implementation or operational execution processes, not Change Management itself; monitoring progress (B) is a control/monitoring activity, and managing the actual implementation (C) is an execution concern - both happen after the Change Management decision is made. A helpful memory tip: think of Change Management as the boardroom, not the construction site - it decides what gets built (the correct decision on information provisioning), while other processes handle the actual building and oversight.
Topics
Community Discussion
No community discussion yet for this question.