Which activity belongs to the process Specify information requirements?

The correct answer is B. defining the impact of the suggested IT solution on the end user organization. Specifying information requirements is about bridging business needs and IT solutions from the user's perspective - it focuses on what end users need from information systems and how a proposed solution will affect their daily work. Option B fits squarely here because assessing…

Information Management Process

Question

Which activity belongs to the process Specify information requirements?

Options

  • Adefining the global impact of a suggested change to the information provisioning
  • Bdefining the impact of the suggested IT solution on the end user organization
  • Cdefining how the IT solution interacts with the non-automated processes

How the community answered

(29 responses)
  • A
    3% (1)
  • B
    93% (27)
  • C
    3% (1)

Explanation

Specifying information requirements is about bridging business needs and IT solutions from the user's perspective - it focuses on what end users need from information systems and how a proposed solution will affect their daily work. Option B fits squarely here because assessing the impact on the end user organization is a core part of translating business needs into information requirements.

Option A is wrong because evaluating the global impact of a change to information provisioning belongs to a change management or impact analysis process - it's broader in scope and organizational level than specifying requirements.

Option C is wrong because defining how an IT solution interacts with non-automated processes is a technical design or process integration concern, typically belonging to "Specify IT requirements" or a solution design activity rather than the information requirements phase.

Memory tip: Think of "Specify information requirements" as the user-side process - if the activity centers on what users need or how they're affected, it likely belongs here. If it's about technical interactions or org-wide change governance, it belongs elsewhere.

Topics

#Specify information requirements#IT solution impact#end user organization#process activity