What is a result of the process Specify information requirement?
The correct answer is B. a list of functional and non-functional demands. Option B is correct because "Specify information requirement" is a requirements-gathering process whose primary output is a structured list of what the system must do (functional demands) and how well it must do it (non-functional demands, e.g., performance, security). The…
Question
What is a result of the process Specify information requirement?
Options
- Aa functional design
- Ba list of functional and non-functional demands
- Can approved test strategy
How the community answered
(33 responses)- A3% (1)
- B94% (31)
- C3% (1)
Explanation
Option B is correct because "Specify information requirement" is a requirements-gathering process whose primary output is a structured list of what the system must do (functional demands) and how well it must do it (non-functional demands, e.g., performance, security). The process is about capturing needs, not yet designing or validating solutions.
Option A (functional design) is wrong because a functional design is an output of a design process that comes after requirements are specified - it describes how requirements will be implemented, not what they are.
Option C (an approved test strategy) is wrong because a test strategy is an output of a test planning process, which uses the requirements list as input - it cannot exist before the requirements are defined.
Memory tip: Think of the process name literally - "Specify" = write down what you need. The output must be a list of needs (demands), not a solution (design) or a validation plan (test strategy). Requirements come before design, which comes before testing.