EX0-008 · Question #63

A team estimates a Story using the Planning Poker technique. The team decides to allocate five Story points to the Story, because the Developers estimated two points and the Testers estimated three…

The correct answer is B. Points are assigned for the overall Story, not for parts of the Story. In Planning Poker, story points represent the total effort for the entire story as a unified estimate agreed upon by the whole team - not a sum of individual role-based estimates. Splitting points by "Developers get 2, Testers get 3" misunderstands the technique; the team…

Scrum Developer Role

Question

A team estimates a Story using the Planning Poker technique. The team decides to allocate five Story points to the Story, because the Developers estimated two points and the Testers estimated three points. Which statement is true regarding this scenario?

Options

  • APoints are assigned by the Scrum Master, not by the team.
  • BPoints are assigned for the overall Story, not for parts of the Story.
  • CPoints are never estimated, but always determined beforehand.
  • DThe team forgets to ask the Product Owner about the estimate.

How the community answered

(24 responses)
  • B
    88% (21)
  • C
    4% (1)
  • D
    8% (2)

Explanation

In Planning Poker, story points represent the total effort for the entire story as a unified estimate agreed upon by the whole team - not a sum of individual role-based estimates. Splitting points by "Developers get 2, Testers get 3" misunderstands the technique; the team should discuss until reaching consensus on one number for the whole story.

Why the distractors are wrong:

  • A is incorrect because the Scrum Master facilitates but does not assign story points - estimation is a Developer team responsibility.
  • C is incorrect because story points are always estimated collaboratively, not predetermined.
  • D is a red herring; the Product Owner clarifies scope and acceptance criteria but does not participate in the effort estimate itself.

Memory tip: Think of a story point like a price tag on a complete meal - you don't separately price the chef's labor, the dishwasher's time, and the server's time and add them up. You price the meal as one thing. Story points = one estimate for the whole story, not a sum of parts.

Topics

#Planning Poker#story points#estimation#Sprint Planning