EX0-008 · Question #21

What is meant by the velocity of the team?

The correct answer is C. The rate at which the team completes the work. Velocity in an Agile/Scrum context measures how much work a team completes in a given iteration (sprint), making C correct - it captures the team's throughput of work items (typically story points or tasks) over time. Why the distractors are wrong: A is wrong because velocity…

Scrum Developer Role

Question

What is meant by the velocity of the team?

Options

  • AThe rate a team puts in a normal work day.
  • BThe rate at which features are released to the customer.
  • CThe rate at which the team completes the work.
  • DThe rate at which the team renews itself.

How the community answered

(41 responses)
  • B
    5% (2)
  • C
    93% (38)
  • D
    2% (1)

Explanation

Velocity in an Agile/Scrum context measures how much work a team completes in a given iteration (sprint), making C correct - it captures the team's throughput of work items (typically story points or tasks) over time.

Why the distractors are wrong:

  • A is wrong because velocity isn't about hours worked in a day - it measures output, not effort or attendance.
  • B is close but wrong - releasing features to customers is about deployment frequency or throughput to production, not velocity, which is an internal planning metric.
  • D is wrong - team renewal (turnover/onboarding) is a team health metric, unrelated to velocity.

Memory tip: Think of velocity like a car's speedometer - it tells you how fast you're covering ground (work), not how long you drove, where you delivered, or who's in the car.

Topics

#velocity#team metrics#sprint completion#agile measurement