EX0-008 · Question #58

A user story was estimated at five ideal hours. On a normal eight hour working day, the team gets about four hours of actual work time. What would be the elapsed time required to complete the Story?

The correct answer is A. One day and two hours. Option A is correct because ideal hours measure pure focused work time, not clock time. With only 4 productive hours available per 8-hour day, completing 5 ideal hours requires 5 ÷ 4 = 1.25 days - which equals 1 full day (8 hours elapsed) plus 2 additional hours, totaling 1 day…

Scrum Developer Role

Question

A user story was estimated at five ideal hours. On a normal eight hour working day, the team gets about four hours of actual work time. What would be the elapsed time required to complete the Story?

Options

  • AOne day and two hours
  • BTwo days
  • CFive hours

How the community answered

(66 responses)
  • A
    74% (49)
  • B
    15% (10)
  • C
    11% (7)

Explanation

Option A is correct because ideal hours measure pure focused work time, not clock time. With only 4 productive hours available per 8-hour day, completing 5 ideal hours requires 5 ÷ 4 = 1.25 days - which equals 1 full day (8 hours elapsed) plus 2 additional hours, totaling 1 day and 2 hours of elapsed time.

Option C (Five hours) is wrong because it confuses ideal time with elapsed time - you can't complete 5 hours of focused work in 5 clock hours when you only have 4 productive hours per day.

Option B (Two days) overcounts - two full days would give you 8 productive hours, but the story only requires 5 ideal hours, so you finish partway through the second day.

Memory tip: Think of it as a unit conversion - divide ideal hours by your daily productive hours to get days, then convert the decimal remainder back to clock hours. The formula is: elapsed time = ideal hours ÷ (productive hours/day).

Topics

#ideal hours#elapsed time#velocity#estimation