EX0-008 · Question #59

Who knows most about the progress towards a business objective or a release?

The correct answer is A. The Product Owner. A is correct because the Product Owner (PO) owns the Product Backlog and is responsible for maximizing product value - they track progress toward the product goal, manage release forecasts, and communicate status to stakeholders. The PO holds the vision and the metrics. B is…

Product Owner Role

Question

Who knows most about the progress towards a business objective or a release?

Options

  • AThe Product Owner
  • BThe Scrum Master
  • CThe team

How the community answered

(21 responses)
  • A
    95% (20)
  • B
    5% (1)

Explanation

A is correct because the Product Owner (PO) owns the Product Backlog and is responsible for maximizing product value - they track progress toward the product goal, manage release forecasts, and communicate status to stakeholders. The PO holds the vision and the metrics.

B is wrong because the Scrum Master focuses on process health and removing impediments, not on what is or isn't delivered toward a business objective.

C is wrong because while the Development Team knows their own sprint velocity and technical progress, they don't own the business objective or release roadmap - that accountability lives with the PO.

Memory tip: Think "Product Owner = Product Progress." Whoever owns the goal owns the knowledge of how far along it is. The PO is the single wringable neck for "are we on track to release?"