EX0-008 · Question #51
Near the end of a Sprint, the team realizes that they will not be able to complete the stories they had committed to. What is the best course of action for the team?
The correct answer is B. Ask the Product Owner to decide which stories can be delayed until the next Sprint. Option B is correct because in Scrum, the Product Owner (PO) owns the Product Backlog and has the authority to prioritize and re-scope work. When a Sprint is at risk, the PO decides which stories deliver the most value and which can be deferred - this is a core Scrum…
Question
Near the end of a Sprint, the team realizes that they will not be able to complete the stories they had committed to. What is the best course of action for the team?
Options
- AAdd resources and team members to meet the goals of the current Sprint.
- BAsk the Product Owner to decide which stories can be delayed until the next Sprint.
- CDecide on a new definition of 'done' for the Sprint Backlog Items.
How the community answered
(56 responses)- A18% (10)
- B75% (42)
- C7% (4)
Explanation
Option B is correct because in Scrum, the Product Owner (PO) owns the Product Backlog and has the authority to prioritize and re-scope work. When a Sprint is at risk, the PO decides which stories deliver the most value and which can be deferred - this is a core Scrum responsibility, not a team decision.
Why the distractors are wrong:
- A is wrong because adding resources mid-Sprint violates Scrum principles - the team's composition should remain stable, and the "mythical man-month" problem means new members slow teams down short-term, not speed them up.
- C is wrong because changing the definition of "done" to accommodate incomplete work undermines quality and defeats the purpose of having a consistent DoD. This creates technical debt and misrepresents what was actually completed.
Memory tip: Think of the PO as the business decision-maker for scope. Whenever a question involves cutting, adding, or reprioritizing work, the PO holds that power - the team executes, but the PO directs what gets delivered.
Topics
Community Discussion
No community discussion yet for this question.