EX0-008 · Question #50
During a Sprint Planning session, the team argues about the work estimates for a particular story. - The Product Owner estimates five days. - The Lead Architect estimates two days. - The Scrum…
The correct answer is C. 7. In Scrum, estimates must come from the person who will actually do the work - making the assigned team member's estimate of 7 days the correct value to use. This is a core Agile principle: those closest to the implementation have the most accurate understanding of effort and…
Question
During a Sprint Planning session, the team argues about the work estimates for a particular story.
- The Product Owner estimates five days.
- The Lead Architect estimates two days.
- The Scrum Master estimates eight days.
- The team member working on it estimates seven days.
What value (in days) should be used for planning?
Options
- A2
- B5
- C7
- D8
How the community answered
(33 responses)- A6% (2)
- B9% (3)
- C82% (27)
- D3% (1)
Explanation
In Scrum, estimates must come from the person who will actually do the work - making the assigned team member's estimate of 7 days the correct value to use. This is a core Agile principle: those closest to the implementation have the most accurate understanding of effort and complexity.
- A (2 days) is wrong because the Lead Architect is not doing the work; their estimate likely underestimates hidden complexity the implementer knows about.
- B (5 days) is wrong because the Product Owner defines what gets built, not how long it takes - the PO should not be estimating implementation effort at all.
- D (8 days) is wrong because the Scrum Master is a process facilitator, not a technical contributor; they have no basis for work estimates.
Memory tip: Think "Who owns the work owns the estimate." If you see a story where multiple roles give different estimates, always pick the developer/implementer - they have the ground-level knowledge that managers and architects lack.