During a Sprint Planning session, the team argues about the work estimates for a particular story. - The Product Owner estimates five days. - The Lead Architect estimates two days. - The Scrum…

The correct answer is C. 7. In Scrum, estimates must come from the person who will actually do the work - making the assigned team member's estimate of 7 days the correct value to use. This is a core Agile principle: those closest to the implementation have the most accurate understanding of effort and…

Scrum Events

Question

During a Sprint Planning session, the team argues about the work estimates for a particular story.

  • The Product Owner estimates five days.
  • The Lead Architect estimates two days.
  • The Scrum Master estimates eight days.
  • The team member working on it estimates seven days.

What value (in days) should be used for planning?

Options

  • A2
  • B5
  • C7
  • D8

How the community answered

(33 responses)
  • A
    6% (2)
  • B
    9% (3)
  • C
    82% (27)
  • D
    3% (1)

Explanation

In Scrum, estimates must come from the person who will actually do the work - making the assigned team member's estimate of 7 days the correct value to use. This is a core Agile principle: those closest to the implementation have the most accurate understanding of effort and complexity.

  • A (2 days) is wrong because the Lead Architect is not doing the work; their estimate likely underestimates hidden complexity the implementer knows about.
  • B (5 days) is wrong because the Product Owner defines what gets built, not how long it takes - the PO should not be estimating implementation effort at all.
  • D (8 days) is wrong because the Scrum Master is a process facilitator, not a technical contributor; they have no basis for work estimates.

Memory tip: Think "Who owns the work owns the estimate." If you see a story where multiple roles give different estimates, always pick the developer/implementer - they have the ground-level knowledge that managers and architects lack.

Topics

#estimation#Sprint Planning#team ownership#story points