The team determines that it has over-committed itself for a Sprint. Who should be present when reviewing and adjusting the Sprint work?
Sign in or unlock EX0-008 to reveal the answer and full explanation for question #16. The question stem and answer options stay visible for context.
Scrum Events
Question
The team determines that it has over-committed itself for a Sprint. Who should be present when reviewing and adjusting the Sprint work?
Options
- AThe team, the Scrum Master and the Product Owner. The Stakeholders should be consulted.
- BThe team and the Scrum Master. The Product Owner should be consulted.
- CThe team only. The Product Owner should be consulted.