EX0-008 · Question #33
Under what circumstances would a team use Affinity Estimation Technique instead of Planning Poker?
The correct answer is B. If there is a large number of stories to estimate. Affinity Estimation is designed for speed and scale - teams group stories by relative size (like T-shirt sizing) without deep discussion, making it ideal when there are many stories to estimate quickly, which is why B is correct. Option A is wrong because needing more details…
Question
Under what circumstances would a team use Affinity Estimation Technique instead of Planning Poker?
Options
- AIf more details are needed during Sprint Planning
- BIf there is a large number of stories to estimate
- CIf there is a small number of stories to estimate
How the community answered
(42 responses)- A7% (3)
- B90% (38)
- C2% (1)
Explanation
Affinity Estimation is designed for speed and scale - teams group stories by relative size (like T-shirt sizing) without deep discussion, making it ideal when there are many stories to estimate quickly, which is why B is correct. Option A is wrong because needing more details during Sprint Planning is actually a signal to use Planning Poker, which drives deeper conversation and shared understanding through structured debate. Option C is the opposite of the right scenario - with a small number of stories, Planning Poker is perfectly manageable and gives richer consensus on each item.
Memory tip: Think "Affinity = Army" - you use it when you have an army of stories to get through fast, while Planning Poker is for smaller battles where every card played sparks a discussion.