Question

A Project Manager wants to track not just the rate of progress against tasks, but also the overall morale and happiness of the Scrum team. What device will help track morale and happiness?

Options

  • AA Gross Happiness index
  • BA Niko-niko calendar
  • CAn employee satisfaction survey