EX0-008 · Question #24
A customer requests a report that summarizes functionality added and defects found and fixed, right at the end of a Sprint. Who may best prepare this report?
The correct answer is B. The Scrum Master. The Scrum Master's role includes facilitating transparency and communication across the team and stakeholders, making them the most appropriate person to compile and present a summary report of Sprint outcomes such as new functionality and defect activity. The Product Owner (A)…
Question
A customer requests a report that summarizes functionality added and defects found and fixed, right at the end of a Sprint. Who may best prepare this report?
Options
- AThe Product Owner
- BThe Scrum Master
- CThe team
- DThis type of report should not be prepared.
How the community answered
(52 responses)- A15% (8)
- B71% (37)
- C4% (2)
- D10% (5)
Explanation
The Scrum Master's role includes facilitating transparency and communication across the team and stakeholders, making them the most appropriate person to compile and present a summary report of Sprint outcomes such as new functionality and defect activity. The Product Owner (A) focuses on backlog prioritization and product vision - their lens is on what comes next, not documenting what was completed. The Development Team (C) is responsible for delivering the work itself; burdening them with report preparation at Sprint end distracts from Sprint Review participation and Retrospective engagement. Option D (no report) is tempting if you're thinking of pure Scrum, where the Sprint Review meeting replaces formal reports - but this question asks who best prepares one if required, so eliminating all options isn't the right move here.
Memory tip: Think of the Scrum Master as the "process steward" - anything related to tracking, transparency, and communicating team progress to the organization falls in their lane, even if it's not a Scrum artifact by name.