EX0-002 · Question #83

When considering how long the project stages should be, which might be a reason for one stage to be longer than others?

The correct answer is C. The risk is lower. See the full explanation below for the reasoning.

Question

When considering how long the project stages should be, which might be a reason for one stage to be longer than others?

Options

  • AA substantial amount of the project budget is to be spent
  • BMore human resources are required than in other stages
  • CThe risk is lower
  • DNo changes to the project management team are envisaged

How the community answered

(47 responses)
  • A
    13% (6)
  • B
    9% (4)
  • C
    74% (35)
  • D
    4% (2)