EX0-002 · Question #82

EX0-002 Question #82: Real Exam Question with Answer & Explanation

The correct answer is B. It is forecast that project level tolerance will be exceeded. See the full explanation below for the reasoning.

Question

When should the Project Board refer to corporate or programme management for a decision?

Options

  • AThe stage requires resources
  • BIt is forecast that project level tolerance will be exceeded
  • CThe Senior Supplier or Senior User needs to be changed
  • DAny request for change needs to be approved