Which role is responsible for specifying the project benefits?

The correct answer is C. Senior User(s). See the full explanation below for the reasoning.

Question

Which role is responsible for specifying the project benefits?

Options

  • ACorporate or programme management
  • BExecutive
  • CSenior User(s)
  • DProject Manager

How the community answered

(28 responses)
  • A
    7% (2)
  • B
    7% (2)
  • C
    71% (20)
  • D
    14% (4)