EX0-002 · Question #64

EX0-002 Question #64: Real Exam Question with Answer & Explanation

The correct answer is B. preventing poorly-conceived projects from ever being initiated. See the full explanation below for the reasoning.

Question

Identify the missing words in the following sentence. The purpose of the Starting up a Project process is as much about [?] as it is about requesting authorization to initiate viable projects,

Options

  • Aproducing an achievable Project Plan
  • Bpreventing poorly-conceived projects from ever being initiated
  • Cobtaining approval from all stakeholders
  • Dsetting up the required project controls