EX0-002 · Question #150

If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?

The correct answer is C. Issue Report. See the full explanation below for the reasoning.

Question

If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?

Options

  • ACheckpoint Report
  • BHighlight Report
  • CIssue Report
  • DProduct Status Account

How the community answered

(53 responses)
  • A
    11% (6)
  • B
    6% (3)
  • C
    81% (43)
  • D
    2% (1)