Which is NOT an objective of the Controlling a Stage process?

The correct answer is C. Update the Business Case with any changes agreed with the Project Board. See the full explanation below for the reasoning.

Question

Which is NOT an objective of the Controlling a Stage process?

Options

  • AImplement actions to control the impact of risks that occur during the stage
  • BReview the Business Case at regular intervals to assess the impact of changes that occur during
  • CUpdate the Business Case with any changes agreed with the Project Board
  • DCoordinate the delivery of products as agreed in the Stage Plan