nerdexam
EXIN

EX0-002 · Question #127

Which PRINCE2 role has a specific responsibility for ensuring that the quality activities relating to products at all stages has appropriate user representation?

The correct answer is C. Project Assurance. See the full explanation below for the reasoning.

Question

Which PRINCE2 role has a specific responsibility for ensuring that the quality activities relating to products at all stages has appropriate user representation?

Options

  • AProject Manager
  • BExecutive
  • CProject Assurance
  • DQuality Assurance

How the community answered

(47 responses)
  • A
    6% (3)
  • B
    11% (5)
  • C
    81% (38)
  • D
    2% (1)

Community Discussion

No community discussion yet for this question.

Full EX0-002 Practice