EXIN
EX0-002 · Question #126
Which PRINCE2 role has a specific responsibility for checking that the project remains aligned to the corporate or programme strategy?
The correct answer is B. Project Assurance. See the full explanation below for the reasoning.
Question
Which PRINCE2 role has a specific responsibility for checking that the project remains aligned to the corporate or programme strategy?
Options
- AProject Manager
- BProject Assurance
- CSenior User
- DSenior Supplier
How the community answered
(51 responses)- A2% (1)
- B82% (42)
- C10% (5)
- D6% (3)
Community Discussion