True or False: On an Agile team, the team members accept or reject their own work at the iteration demo

The correct answer is B. False. See the full explanation below for the reasoning.

Question

True or False: On an Agile team, the team members accept or reject their own work at the iteration demo

Options

  • ATrue
  • BFalse

How the community answered

(28 responses)
  • A
    18% (5)
  • B
    82% (23)