For an Agile or Lean project team, which best describes the aim of the Construction phase?

The correct answer is A. The team develops a consumable solution in a collaborative and incremental manner. See the full explanation below for the reasoning.

Question

For an Agile or Lean project team, which best describes the aim of the Construction phase?

Options

  • AThe team develops a consumable solution in a collaborative and incremental manner
  • BThe team develops software, releasing it into production every two weeks
  • CThe team develops new software every two weeks, demoing it to their stakeholders who may
  • DThe team develops software in a collaborative and regular manner

How the community answered

(57 responses)
  • A
    81% (46)
  • B
    5% (3)
  • C
    2% (1)
  • D
    12% (7)