Using Lean thinking, we should be managing
The correct answer is A. The value stream. See the full explanation below for the reasoning.
Question
Using Lean thinking, we should be managing
Options
- AThe value stream
- BEach step of the work
- COur people
- DBy letting people figure out what they need to do
How the community answered
(45 responses)- A76% (34)
- B13% (6)
- C4% (2)
- D7% (3)