DASSM · Question #122

Who is responsible for choosing the team's lifecycle?

The correct answer is B. The team members. See the full explanation below for the reasoning.

Question

Who is responsible for choosing the team's lifecycle?

Options

  • AThe team's Agile coach
  • BThe team members
  • CIt depends on the context
  • DThe team's manager

How the community answered

(47 responses)
  • A
    2% (1)
  • B
    77% (36)
  • C
    13% (6)
  • D
    9% (4)