nerdexam
GAQM

CSM-001 · Question #71

Development Team members volunteer to own a Sprint Backlog item: Backlog:

The correct answer is C. Never. All Sprint Backlog Items are "owned" by the entire Development Team, even though each. See the full explanation below for the reasoning.

Question

Development Team members volunteer to own a Sprint Backlog item:

Backlog:

Options

  • ADuring the Daily Scrum
  • BWhenever a team member can accommodate more work
  • CNever. All Sprint Backlog Items are "owned" by the entire Development Team, even though each
  • DAt the Sprint planning meeting

How the community answered

(27 responses)
  • A
    11% (3)
  • B
    4% (1)
  • C
    78% (21)
  • D
    7% (2)

Community Discussion

No community discussion yet for this question.

Full CSM-001 Practice