CSM-001 · Question #70

Which three activities will a Product Owner likely engage in during a Sprint?

The correct answer is B. Answer questions from the Development Team about items in the current Sprint D. Work with the stakeholders F. Provide feedback. See the full explanation below for the reasoning.

Question

Which three activities will a Product Owner likely engage in during a Sprint?

Options

  • ARun the daily Scrum
  • BAnswer questions from the Development Team about items in the current Sprint
  • CUpdate the Sprint burndown chart
  • DWork with the stakeholders
  • EPrioritize the Development Team's activities.
  • FProvide feedback

How the community answered

(34 responses)
  • A
    6% (2)
  • B
    79% (27)
  • C
    12% (4)
  • E
    3% (1)

Community Discussion

No community discussion yet for this question.