You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8hours. The team has just enough time to complete all tasks in the remaining16 hours with the…

The correct answer is A. The development team should negotiate with the Product Owner on the definition of "done". See the full explanation below for the reasoning.

Question

You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8hours. The team has just enough time to complete all tasks in the remaining16 hours with the exception ofthree tasks. Of these three tasks, two tasks (a total of 6 hours) are requiredto complete one Product Backlogitem and one task (an estimate of 2 hours) is required to complete another Product Backlog item. How shouldthe development team handle the remaining three tasks?

Options

  • AThe development team should negotiate with the Product Owner on the definition of "done".
  • BThe development team should work the extra 8 hours to complete their commitment to the
  • CThe development team should place the two Product Backlog items back onto the Product
  • DThe development team should keep the three tasks on the Sprint Backlog for the next Sprint and

How the community answered

(50 responses)
  • A
    84% (42)
  • B
    4% (2)
  • C
    2% (1)
  • D
    10% (5)