GAQM
CSM-001 · Question #115
You are the Scrum Master and the very first Sprint will complete in 5 days. You are creating a meeting invite forthe Sprint Review to demo the items completed in the Sprint. Who should you invite as…
The correct answer is B. 1 and 2 only. See the full explanation below for the reasoning.
Question
You are the Scrum Master and the very first Sprint will complete in 5 days. You are creating a meeting invite forthe Sprint Review to demo the items completed in the Sprint. Who should you invite as a required attendee tothe Sprint Review? 1. Product Owner(s) 2. Development Team 3. Business Users
Options
- A1, 2, and 3
- B1 and 2 only
- CThe entire company
- D1 only
How the community answered
(31 responses)- A3% (1)
- B77% (24)
- C6% (2)
- D13% (4)
Community Discussion