nerdexam
Salesforce

CRT-261 · Question #82

CRT-261 Question #82: Real Exam Question with Answer & Explanation

The correct answer is B. Prepare a change order to account for the additional requirements and communicate the new. When additional requirements are discovered that impact the project's timeline and budget, preparing a change order to account for these requirements is the first step. This involves adjusting the project scope, timeline, and budget to accommodate the new requirements, ensuring t

Question

A consultant is working on a Service Cloud implementation with a fixed budget and timeline. Additional requirements were discovered early on that will result in the project exceeding timeline and budget constraints. What is the first step the consultant should take to address the issue?

Options

  • AIncorporate the additional requirements to the project scope and continue with the original project
  • BPrepare a change order to account for the additional requirements and communicate the new
  • CDocument the gap in requirements and discuss the schedule and budget Impact with the project

Explanation

When additional requirements are discovered that impact the project's timeline and budget, preparing a change order to account for these requirements is the first step. This involves adjusting the project scope, timeline, and budget to accommodate the new requirements, ensuring that all stakeholders are aligned and informed about the changes and implications for the project's delivery.

Community Discussion

No community discussion yet for this question.

Full CRT-261 Practice