ASQ
CQIA · Question #55
At what point should capacity requirements of a proposed system be first considered?
The correct answer is B. As early as possible. You've hit your limit · resets 12:50am (America/New_York)
Continuous Improvement
Question
At what point should capacity requirements of a proposed system be first considered?
Options
- ALeave it until the system is implemented and see if the system works O.K.
- BAs early as possible
- CWhen the Development Manager has completed testing and passes the system to Operations for
- DJust before the system goes live
How the community answered
(66 responses)- A2% (1)
- B89% (59)
- C6% (4)
- D3% (2)
Explanation
You've hit your limit · resets 12:50am (America/New_York)
Topics
#Capacity Management#capacity planning#proactive management#system implementation
Community Discussion