A major problem has occurred that was not identified in the risk response plan. What is the term used to identify the actions to deal with these unplanned risks?

The correct answer is B. Workaround. See the full explanation below for the reasoning.

Management and Leadership in Quality Engineering

Question

A major problem has occurred that was not identified in the risk response plan. What is the term used to identify the actions to deal with these unplanned risks?

Options

  • AIssue
  • BWorkaround
  • COpportunity
  • DRisk identification

How the community answered

(38 responses)
  • A
    8% (3)
  • B
    74% (28)
  • C
    16% (6)
  • D
    3% (1)

Topics

#workaround#unplanned risk#risk response plan#risk management