You are shifting your plant to an earthquake prone location. You get plant foundations designed to absorb the earthquake shocks. What risk strategy are you adopting?

The correct answer is A. Mitigate. See the full explanation below for the reasoning.

Management and Leadership in Quality Engineering

Question

You are shifting your plant to an earthquake prone location. You get plant foundations designed to absorb the earthquake shocks. What risk strategy are you adopting?

Options

  • AMitigate
  • BAvoid
  • CTransfer
  • DAccept

How the community answered

(31 responses)
  • A
    71% (22)
  • B
    16% (5)
  • C
    6% (2)
  • D
    6% (2)

Topics

#risk mitigation#risk strategy#risk response#risk management