CQE · Question #1

A vendor may be audited both before and during the execution of a contract. During such a vendor audit, the focus may be directed at the management and resource management of the company. Which of…

The correct answer is D. Design and process capabilities. See the full explanation below for the reasoning.

The Quality System

Question

A vendor may be audited both before and during the execution of a contract. During such a vendor audit, the focus may be directed at the management and resource management of the company. Which of the following areas would be EXCLUDED during such an audit?

Options

  • AUse and planning of time, manpower and training.
  • BDefined quality responsibilities.
  • CCompany philosophy and organizational charts.
  • DDesign and process capabilities.

How the community answered

(37 responses)
  • A
    5% (2)
  • B
    3% (1)
  • C
    14% (5)
  • D
    78% (29)

Topics

#vendor audit#audit scope#resource management#supplier management