CQE · Question #19

A purchase order for subassemblies classified as critical must include a review by

The correct answer is D. I, II and III. See the full explanation below for the reasoning.

The Quality System

Question

A purchase order for subassemblies classified as critical must include a review by

Options

  • AIII only
  • BI and III only
  • CII and III only
  • DI, II and III
  • IQuality engineering.

How the community answered

(53 responses)
  • A
    11% (6)
  • B
    2% (1)
  • C
    2% (1)
  • D
    79% (42)
  • I
    6% (3)

Topics

#purchase order#critical components#supplier control#procurement review

Community Discussion

No community discussion yet for this question.