ASQ
CQE · Question #47
A comprehensive corrective action program is initiated at a large company. Inputs for CARs are received from customers, internal and external audits, material review reports and other sources. Which…
The correct answer is B. I and III only. See the full explanation below for the reasoning.
The Quality System
Question
A comprehensive corrective action program is initiated at a large company. Inputs for CARs are received from customers, internal and external audits, material review reports and other sources. Which two of the following groups would usually administer and control the CAR process?
Options
- AI and II only
- BI and III only
- CII and III only
- DIII and IV only
- IManagement review team.
How the community answered
(39 responses)- A3% (1)
- B72% (28)
- C15% (6)
- D8% (3)
- I3% (1)
Topics
#corrective action request#CAR process#audit management#quality system administration