CCBA · Question #641

In the Requirements and Design cycle, the business analyst is looking into the Business requirements now. What should be the next step for the business analyst in this Requirements and Design cycle?

The correct answer is A. Stakeholder Requirementsright. The sequence of steps in the Requirements and Design cycle are Business Requirements, Stakeholder Requirements, Solution Requirements and Transition Requirements. Choice A is correct, since Stakeholder Requirements is the next step after Business Requirements for the business ana

Requirements Life Cycle Management

Question

In the Requirements and Design cycle, the business analyst is looking into the Business requirements now. What should be the next step for the business analyst in this Requirements and Design cycle?

Options

  • AStakeholder Requirementsright
  • BSolution Requirements
  • CTransition Requirements
  • DNone of the above

How the community answered

(43 responses)
  • A
    93% (40)
  • B
    5% (2)
  • D
    2% (1)

Explanation

The sequence of steps in the Requirements and Design cycle are Business Requirements, Stakeholder Requirements, Solution Requirements and Transition Requirements. Choice A is correct, since Stakeholder Requirements is the next step after Business Requirements for the business analyst in this Requirements and Design cycle. Choice B is not correct, since Solutions Requirements is not the next step after Business Requirements for the business analyst in this Requirements and Design cycle. Choice C is not correct, since Transition Requirements is not the next step after Business Requirements for the business analyst in this Requirements and Design cycle. Choice D is not correct, since choice A is correct.

Topics

#requirements hierarchy#requirements types#stakeholder requirements#requirements cycle