A change is desired in a project after the requirements are signed off and after technical design has started. The stakeholders want an additional product to be developed as part of the project…

The correct answer is D. Requirements architecture. Requirements architecturehelps the BA assesshow the new change affects existing requirements, design, dependencies, and constraints. BABOK® Guide (Chapter 7.1 - Define Requirements Architecture)states that requirements architectureshows relationships between requirements…

Requirements Life Cycle Management

Question

A change is desired in a project after the requirements are signed off and after technical design has started. The stakeholders want an additional product to be developed as part of the project. What tool can be used by the business analyst (BA) to assess the impact of the change?

Options

  • ABacklog management
  • BBalanced scorecard
  • CConcept modeling
  • DRequirements architecture

How the community answered

(48 responses)
  • A
    6% (3)
  • B
    4% (2)
  • C
    17% (8)
  • D
    73% (35)

Explanation

Requirements architecturehelps the BA assesshow the new change affects existing requirements, design, dependencies, and constraints. BABOK® Guide (Chapter 7.1 - Define Requirements Architecture)states that requirements architectureshows relationships between requirements, allowing impact analysis to be performed efficiently. Backlog management (Option A)is useful for tracking work in Agile but does not provide impact Balanced scorecard (Option B)helps measure organizational performance, not changes to Concept modeling (Option C)defines relationships between ideas but does not evaluate change

Topics

#change impact assessment#requirements architecture#scope management#requirements traceability