CCBA · Question #559
Stakeholders initially agreed to an implementation schedule for a set of reports based on the value to business users. The development team provided a detailed estimate of the time required to…
The correct answer is A. Review the priorities. Since the implementation timeline is affected, thepriorities should be reviewedto align with business value and feasibility. The BABOK® Guide (Chapter 5.1 - Prioritize Requirements)states thatprioritization should be adjusted based on constraints such as development time…
Question
Stakeholders initially agreed to an implementation schedule for a set of reports based on the value to business users. The development team provided a detailed estimate of the time required to develop each report based on the business requirements. What should the business analyst (BA) and the stakeholders do with the estimates?
Options
- AReview the priorities.
- BAnalyze technical constraints.
- CRevise the business requirements.
- DWrite functional report specifications.
How the community answered
(16 responses)- A75% (12)
- B6% (1)
- C13% (2)
- D6% (1)
Explanation
Since the implementation timeline is affected, thepriorities should be reviewedto align with business value and feasibility. The BABOK® Guide (Chapter 5.1 - Prioritize Requirements)states thatprioritization should be adjusted based on constraints such as development time, costs, and
Topics
Community Discussion
No community discussion yet for this question.