CCBA · Question #553

A project has experienced several schedule delays. A business analyst (BA) is assigned to the project to help get it back on track. The project manager believes that incomplete requirements are…

The correct answer is B. Quality control checklist. A quality control check list helps identify gaps, inconsistencies, and missing requirements, which might be causing the delays. The BABOK® Guide (Chapter 5.4 - Verify Requirements)states thatusing structured verification techniques ensures that requirements are complete and…

Requirements Life Cycle Management

Question

A project has experienced several schedule delays. A business analyst (BA) is assigned to the project to help get it back on track. The project manager believes that incomplete requirements are causing the missed milestones. What tool will help address the project manager's concern?

Options

  • ARisk review
  • BQuality control checklist
  • CDecision analysis
  • DCommunication plan

How the community answered

(35 responses)
  • A
    3% (1)
  • B
    74% (26)
  • C
    6% (2)
  • D
    17% (6)

Explanation

A quality control check list helps identify gaps, inconsistencies, and missing requirements, which might be causing the delays. The BABOK® Guide (Chapter 5.4 - Verify Requirements)states thatusing structured verification techniques ensures that requirements are complete and correct, reducing rework and delays.

Topics

#requirements completeness#quality checklist#requirements verification#schedule management