CCBA · Question #495

Before selecting a design solution, a company wants to ensure that stakeholder, solution, and transition requirements align to the business requirements and also that the design satisfies the…

The correct answer is A. Requirements Verification. The process that the BA is completing before selecting a design solution is requirements verification. Requirements verification is the process of ensuring that requirements and designs are complete, correct, consistent, clear, feasible, unambiguous, testable, and conform to…

Requirements Life Cycle Management

Question

Before selecting a design solution, a company wants to ensure that stakeholder, solution, and transition requirements align to the business requirements and also that the design satisfies the requirements. What process is the business analyst (BA) completing?

Options

  • ARequirements Verification
  • BRequirements Elicitation
  • CRequirements Engineering
  • DRequirements Validation

How the community answered

(18 responses)
  • A
    94% (17)
  • C
    6% (1)

Explanation

The process that the BA is completing before selecting a design solution is requirements verification. Requirements verification is the process of ensuring that requirements and designs are complete, correct, consistent, clear, feasible, unambiguous, testable, and conform to standards2. It involves checking whether stakeholder, solution, and transition requirements align to the business requirements and whether the design satisfies the requirements. Requirements verification can help to identify and resolve errors, gaps, or inconsistencies in the requirements and designs before they are implemented.

Topics

#requirements verification#alignment#design validation#traceability

Community Discussion

No community discussion yet for this question.