nerdexam
IIBA

CCBA · Question #45

You're organizing the business analysis approach for your organization. Jane wants to know when changes to requirements are most likely to happen in business analysis processes. Which one of the follo

The correct answer is C. Changes to requirements may happen at any time.. Changes to requirements may happen at any time during the business analysis processes, as new information, feedback, issues, or opportunities arise. The business analyst should be prepared to manage and communicate changes to requirements using a change control system and a trace

Requirements Life Cycle Management

Question

You're organizing the business analysis approach for your organization. Jane wants to know when changes to requirements are most likely to happen in business analysis processes. Which one of the following statements best describes when changes to requirements may happen?

Options

  • AChanges to requirements usually happen at the end of the business analysis processes.
  • BChanges to requirements usually happen early in the business analysis processes.
  • CChanges to requirements may happen at any time.
  • DChanges to requirements happen after the business analysis processes.

How the community answered

(44 responses)
  • A
    7% (3)
  • B
    2% (1)
  • C
    89% (39)
  • D
    2% (1)

Explanation

Changes to requirements may happen at any time during the business analysis processes, as new information, feedback, issues, or opportunities arise. The business analyst should be prepared to manage and communicate changes to requirements using a change control system and a traceability matrix. The business analyst should also ensure that the changes are aligned with the business needs and objectives, and that they do not compromise the quality and value of

Topics

#requirements changes#business analysis process#change management#iterative approach

Community Discussion

No community discussion yet for this question.

Full CCBA Practice