CCBA · Question #398

Requirements have been prioritized in the product backlog for inclusion in the upcoming release. One of the project team members fears that at least one requirement from the prioritization list is not

The correct answer is C. Stability. Stability is the factor that describes the affected requirement, as it indicates the likelihood of the requirement remaining constant and static. Requirements that are not stable or whose definition changes frequently are given a lower priority to minimize recurrence, rework, and

Requirements Life Cycle Management

Question

Requirements have been prioritized in the product backlog for inclusion in the upcoming release. One of the project team members fears that at least one requirement from the prioritization list is not finalized and still requires further analysis. Which of the following factors describe the affected requirement?

Options

  • ABenefit
  • BDependency
  • CStability
  • DRisk

How the community answered

(36 responses)
  • A
    6% (2)
  • B
    3% (1)
  • C
    92% (33)

Explanation

Stability is the factor that describes the affected requirement, as it indicates the likelihood of the requirement remaining constant and static. Requirements that are not stable or whose definition changes frequently are given a lower priority to minimize recurrence, rework, and time and

Topics

#requirement stability#backlog management#prioritization factors#requirement readiness