CCBA · Question #398
Requirements have been prioritized in the product backlog for inclusion in the upcoming release. One of the project team members fears that at least one requirement from the prioritization list is not
The correct answer is C. Stability. Stability is the factor that describes the affected requirement, as it indicates the likelihood of the requirement remaining constant and static. Requirements that are not stable or whose definition changes frequently are given a lower priority to minimize recurrence, rework, and
Question
Requirements have been prioritized in the product backlog for inclusion in the upcoming release. One of the project team members fears that at least one requirement from the prioritization list is not finalized and still requires further analysis. Which of the following factors describe the affected requirement?
Options
- ABenefit
- BDependency
- CStability
- DRisk
How the community answered
(36 responses)- A6% (2)
- B3% (1)
- C92% (33)
Explanation
Stability is the factor that describes the affected requirement, as it indicates the likelihood of the requirement remaining constant and static. Requirements that are not stable or whose definition changes frequently are given a lower priority to minimize recurrence, rework, and time and