CCBA · Question #373

A business analyst (BA) has completed documenting requirements and to save time, recommends sharing the requirements document with the development team to fast-track development immediately. What…

Sign in or unlock CCBA to reveal the answer and full explanation for question #373. The question stem and answer options stay visible for context.

Requirements Life Cycle Management

Question

A business analyst (BA) has completed documenting requirements and to save time, recommends sharing the requirements document with the development team to fast-track development immediately. What issue may arise by doing so?

Options

  • AStakeholders may refuse the solution.
  • BRequirements metrics may not be measurable.
  • CThe BA may significantly impact other aspects of the project timeline.
  • DThe business need may change.

Unlock CCBA to see the answer

You've previewed enough free CCBA questions. Unlock CCBA for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#requirements validation#development handoff#project timeline#requirements approval