A business analyst (BA) is defining a stakeholder approval approach for the requirement deliverables. The project involves implementing new government regulatory requirements with significant risk to
The correct answer is C. Use a rigorous approval process of detailed specifications. The scenario describes a project that involves implementing new government regulatory requirements with significant risk to the organization in case of non-compliance. This implies that the project has high complexity, uncertainty, and stakeholder expectations. Therefore, the BA
Question
A business analyst (BA) is defining a stakeholder approval approach for the requirement deliverables. The project involves implementing new government regulatory requirements with significant risk to the organization in case of non-compliance. According to the BABOK ?GUIDE, what will the BA need to do?
Options
- AEnsure high level user stories are completed and accepted
- BUse an informal approval process to speed up delivery
- CUse a rigorous approval process of detailed specifications
- DEnsure the document is completed and signed off
How the community answered
(46 responses)- A13% (6)
- B2% (1)
- C78% (36)
- D7% (3)
Explanation
The scenario describes a project that involves implementing new government regulatory requirements with significant risk to the organization in case of non-compliance. This implies that the project has high complexity, uncertainty, and stakeholder expectations. Therefore, the BA will need to use a rigorous approval process of detailed specifications to ensure that the requirement deliverables are accurate, complete, and compliant with the regulations. A rigorous approval process involves formal reviews, validations, and sign-offs of the requirement deliverables by the relevant stakeholders, using predefined criteria and standards.