The correct answer is D. The baseline represents the approved requirements and any changes must go through a change. Baseline requirements are the set of requirements that have been formally reviewed and agreed upon by the stakeholders. They serve as a reference point for the development and testing of the solution, as well as for the evaluation of the benefits and value delivered by the soluti
Question
Options
- AThe baseline represents the final collection and approval of all requirements.
- BThe baseline represents the future set of physical deliverables.
- CThe baseline represents the approved set of requirements and no additional changes are
- DThe baseline represents the approved requirements and any changes must go through a change
Explanation
Baseline requirements are the set of requirements that have been formally reviewed and agreed upon by the stakeholders. They serve as a reference point for the development and testing of the solution, as well as for the evaluation of the benefits and value delivered by the solution. Baseline requirements are not final or fixed; they can be changed if there is a valid reason and a proper approval process. Any changes to the baseline requirements must be documented and communicated to the relevant stakeholders, and they must follow a change control system that defines the roles, responsibilities, procedures, and tools for managing changes.