The correct answer is C. Allocate requirements to different releases. This is because when it is not possible to implement all the requirements at once, the BA should prioritize the requirements based on their value, urgency, and dependency, and assign them to different releases or iterations. This way, the most important requirements can be delive
Question
Options
- ARedefine the business requirements associated with each implementation
- BRecommend a reduction in the project scope
- CAllocate requirements to different releases
- DEnsure all requirements are traceable using a matrix
Explanation
This is because when it is not possible to implement all the requirements at once, the BA should prioritize the requirements based on their value, urgency, and dependency, and assign them to different releases or iterations. This way, the most important requirements can be delivered first, and the feedback from the stakeholders can be incorporated in the subsequent releases. Redefining the business requirements (A) is not necessary, as they have already been signed off. Recommending a reduction in the project scope (B) is not a good option, as it may compromise the value and quality of the solution. Ensuring all requirements are traceable using a matrix (D) is a good practice, but it does not address the issue of technical constraints. Reference: CCBA Practice Test, CCBA Mock Test
Community Discussion
No community discussion yet for this question.