CCBA · Question #286
Which one of the following statements best describes requirements prioritization?
The correct answer is D. It determines how requirements will be prioritized and how those priorities will be used to define. Requirements prioritization is the process of assigning relative importance or urgency to the requirements based on various criteria, such as business value, risk, dependency, cost, complexity, stakeholder preference, or regulatory compliance. Requirements prioritization is not l
Question
Which one of the following statements best describes requirements prioritization?
Options
- AIt is only used with the plan-driven approach to business analysis.
- BIt is only used with the change-driven approach to business analysis.
- CIt determines how requirements will be prioritized based on the most important stakeholders to
- DIt determines how requirements will be prioritized and how those priorities will be used to define
How the community answered
(26 responses)- A4% (1)
- B8% (2)
- D88% (23)
Explanation
Requirements prioritization is the process of assigning relative importance or urgency to the requirements based on various criteria, such as business value, risk, dependency, cost, complexity, stakeholder preference, or regulatory compliance. Requirements prioritization is not limited to any specific approach to business analysis, such as plan-driven or change-driven, but it can be applied differently depending on the context and the level of uncertainty. Requirements prioritization helps to determine which requirements are essential, desirable, or optional for the solution scope, and how they will be addressed in the solution delivery. Requirements prioritization also helps to manage the expectations of the stakeholders and to resolve any conflicts or trade-offs among the requirements.
Topics
Community Discussion
No community discussion yet for this question.