CCBA · Question #231
When a business analyst assists in the planning of the solution implementation, she must always consider the constraints for implementation. Which one of the following cannot be considered as an…
The correct answer is A. Weather. According to the BABOK® Guide, an implementation constraint is a restriction or limitation that affects the execution or operation of a solution. Examples of implementation constraints include freeze periods, company policies, business cycle timings, regulatory requirements…
Question
When a business analyst assists in the planning of the solution implementation, she must always consider the constraints for implementation. Which one of the following cannot be considered as an implementation constraint?
Options
- AWeather
- BFreeze periods
- CCompany policies
- DBusiness cycle timings
How the community answered
(46 responses)- A83% (38)
- B4% (2)
- C2% (1)
- D11% (5)
Explanation
According to the BABOK® Guide, an implementation constraint is a restriction or limitation that affects the execution or operation of a solution. Examples of implementation constraints include freeze periods, company policies, business cycle timings, regulatory requirements, and technical standards. Weather is not an implementation constraint because it does not affect the solution itself, but rather the external environment in which the solution operates.