CCBA · Question #114
All of the following stakeholders participate in the prioritization of requirements except for which one?
The correct answer is B. Implementation subject matter expert. The implementation subject matter expert is not a stakeholder who participates in the prioritization of requirements, because they are not directly affected by the business need or the solution. The project team, the domain subject matter expert, and the project manager are all s
Question
All of the following stakeholders participate in the prioritization of requirements except for which one?
Options
- AProject team
- BImplementation subject matter expert
- CDomain subject matter expert
- DProject manager
How the community answered
(20 responses)- A5% (1)
- B90% (18)
- D5% (1)
Explanation
The implementation subject matter expert is not a stakeholder who participates in the prioritization of requirements, because they are not directly affected by the business need or the solution. The project team, the domain subject matter expert, and the project manager are all stakeholders who have a vested interest in the outcome of the project and the value of the solution, and therefore they should be involved in the prioritization of requirements.